Brisbane Technology Park
- 2 – 4 Clunies Ross Court was completed in August 2016.
- Works continue on 29 and 33 Brandl Street, with both buildings due for completion in February 2017.
- The 90 room Quest Hotel will be ready for occupancy in July 2017.
- The multi-deck carparking station behind the Conference Centre, delivering 235 new bays, will be opening in April 2017.
- Detailed design works are underway on two new commercial office buildings within the Innovation Precinct: 1 Clunies Ross Court and 1 Miles Platting Road.

BTP Westlink Green
- Works are now complete on the third stage of the BTP Hub on level 1, 1 Westlink Court totalling 530sqm.
- The development application for the historic QCL Powerhouse building, 3 Westlink court and multi-deck car park has been lodged with Brisbane City Council.

BTP Northshore Hamilton
- The latest addition to the precinct, 375 Macarthur Avenue, is set to open its doors in mid-2017.
- Detailed design works are underway on 381 Macarthur Avenue, an impressive three level, 3,000sqm building with onsite café.

For more information on these projects please contact the BTP Infoline on 07 3368 9099.